KM3NeT - sea campaign

Major upgrade of ARCA’s seafloor network

22 November 2022 – After 4 years of  activities carried out by the Italian funding agency INFN and Alcatel Submarine Networks, part of Nokia, the new subsea network for KM3NeT ARCA, funded under the Idmar regional project in Italy, is now complete.

The new system comprises a 100 km long electro-optical cable, equipped with 48 optical fibres for detector control and data communication and two electrical conductors for power distribution, connected to the shore station control and power feeding equipment, that can deliver up to 80 kW offshore. The cable is bifurcated in order to serve the two building blocks foreseen in ARCA.

During a 10 days long sea operation, which ended on November 17th, a cable termination frame (CTF) was installed on the northern branch of the cable. To this purpose the end of the cable, which was deployed already in 2020, was recovered from the sea floor and connected to the CTF onboard the deployment ship – the Ile d’Ouessant of Alcatel Submarine Networks. Then the CTF was carefully deployed to the target position on the sea floor. Extensive tests were done before and after the deployment to ensure its nominal behaviour.

The CTF is a large-size, 12-ton component which is equipped with four medium voltage converters and a total of 16 electrical and optical subsea connectors for connecting a set of submarine junction boxes to which the detection units will be in turn connected.

With this installation the connectivity and power transmission capabilities of the network have been increased by a factor four compared to the first part of the network, used to run the set of junction boxes and the first 30 detection units of ARCA Phase 1. This will allow for the completion of the construction of the first building block of ARCA and prepares the field for the installation of a second CTF on the other branch of the cable for the second building block.

The CTF at the end of the integration.
CTF onboard Ile d’Ouessant.
Overboarding of the CTF.

Sea campaign for ARCA concluded: welcome, KM3NeT/ARCA19!

14 June 2022 – The sea campaign for enlarging the KM3NeT/ARCA submarine telescope has been completed with full success!

During the last few days, all detection units loaded on Handin Tide for the second phase of the operation were carefully installed on the sea bottom. This was achieved at a record-breaking speed, with 7 detection units installed, connected and unfurled in less than 48 hours!

As a result of the campaign, the size of ARCA has more than doubled. It now comprises 19 detection units in operation, equipped with more than 10,000 photomultipliers,

We thank the teams which worked tirelessly offshore and onshore to reach this remarkable success. And we can’t forget that this was made possible by the hard work ongoing in the almost 30 integration sites of the Collaboration.

The activities at sea went around the clock during the campaign.

The shore station during the campaign – more than 30 people were involved in the onshore team for this campaign.

Welcome KM3NeT/ARCA19

14 June 2022 – The sea campaign for enlarging the KM3NeT/ARCA submarine telescope which was started on June 2, has been completed today with a full success. As a result, data taking with ARCA has been resumed with 19 detection units in operation!

This represents a major step forward for the collaboration, as this was the first time that a 2-weeks campaign was performed. The scope of the operation in fact was twofold: to upgrade the submarine network, by installing 2 new junction boxes in replacement of the junction box that we had been operating so far, and to install 11 new detection units (DUs). The operation therefore took place in two steps: after the first round of activities for installation of the junction boxes and the first 4 DUs, the ship went back to shore to pick up the remaining set of 7 DUs.

The campaign was performed with Handin Tide, of the FUGRO company, which had already performed the previous sea campaign for KM3NeT/ARCA last year, sailing off from Malta.

All planned activities were performed with full success, including ancillary operations such as the replacement of one autonomous acoustic beacon on the sea floor. A speed record was also established, with 7 detection units installed, connected and unfurled in less than 48 hours!

As a result of the campaign, the size of ARCA has more than doubled: It now comprises 19 detection units in operation, equipped with more than 10,000 photomultipliers,

The KM3NeT collaboration wishes to thank the Handin Tide crew for their top-level performance, the KM3NeT teams which worked tirelessly offshore and onshore to reach this remarkable success, as well as all teams which work so hard at the almost 30 integration sites of the collaboration to produce the DUs for building the apparatus.

Below is a gallery of pictures from the campaign. A log of the activities while the operation was ongoing is available on our blog.

Detection units in the port of Malta awaiting deployment.
Loading of a detection unit onto Handin Tide.
Handin Tide leaving Malta for the first phase of the campaign.

Deployment of one of the junction boxes installed in the campaign.

The deck of Handin Tide loaded with DUs for the second phase of the campaign.
Connection of one detection unit on the sea bottom.
The onshore control station at Portopalo di Capo Passero during the campaign. More than 30 people from 10 institutes in France, Italy and the Netherlands participated in the activities onshore.

Activities at sea being resumed at the ARCA site

11 June 2022 – Due to the adverse weather conditions of the last days, the schedule of the sea campaign had to be redefined.

Here is the updated plan:

  • the ship left Malta this afternoon, to be back at the ARCA site tonight
  • the deep sea activities will be started already during the night
  • DU deployments will be started tomorrow
  • end of the operation is foreseen for early next week

Good luck to our offshore and onshore teams!

Empty LOMs (the launcher vehicles used for deployment and unfurling of the detection units) on the dock in the Malta port after the first phase of the sea campaign.
The deck of the Handin Tide loaded with detection units and their cable trays for the second phase of the campaign.
The Handin Tide leaving the port of Malta this afternoon.


Intermediate outcome of the ARCA campaign: 2 junction boxes and 12 detection units operational

6 June 2022 – The first round of activities of the ongoing sea campaign at ARCA has been completed.

In a summary, in the past week-end:

  • we installed two submarine junction boxes, one of which in replacement of the temporary junction box that we have used so far
  • the temporary junction box has been safely recovered
  • we moved all connections of the detection units already installed on the sea bed onto the new junction boxes
  • we installed 4 new detection units (where, by installation, one should understand that each detection unit was lowered to the bottom of the sea, carefully placed on the sea bottom, connected to the junction box and unfurled to reach its nominal, upright configuration)

Each of the steps above comprised dedicated tests, requiring careful coordination of the activities of the onshore and offshore teams.

And… the campaign is not yet finished! The ship is now heading back to Malta to load an additional set of detection units to install.

Stay tuned, as there will be more to report in the next days!

Preparation to deployment of the first detection unit to be installed during the campaign. On the right of it is one of the junction boxes awaiting installation, on the left the temporary junction box recovered from the sea floor.

 

The first detection unit installed in this campaign gracefully splashes into the water, to start its journey down to 3,500 m depth.

 


New sea operation started at ARCA

3 June 2022 – A new sea operation was started yesterday aiming at a significant enlargement of the ARCA neutrino telescope.

This is a major step forward for the Collaboration, as this is the first time ever that we launch a 2-weeks campaign. The scope of the operation in fact is twofold: upgrade the submarine network, by installing 2 brand-new junction boxes in replacement of the junction box that we have been operating so far, and to install new detection units (DUs). The operation will therefore take place in two steps: after the first round of activities for installation of the junction boxes and the first 4 DUs, the ship will come back to shore to pick up an additional set of DUs.

Handin Tide, which has already performed the previous sea campaign for KM3NeT ARCA last year, is the ship which will conduct this operation.

The ship left the port of Malta yesterday afternoon.

Remain connected, as we will be posting news about the operation while the action goes on – on our blog and on our social channels.

A set of KM3NeT DUs ready for deployment in the port of Malta earlier this week.

 

Loading of a KM3NeT DU onto the Handin Tide.

The Handin Tide sailing off from Malta in the afternoon of yesterday, June 2.

Welcome, ORCA-10!

22 November 2021 – Four new detection units have been added to ORCA with a 5-day intense and successful sea operation.

The operation has been performed with two ships: the Castor, equipped for deployment and precise installation of the detection units on the sea floor, and Janus, equipped with a remotely operated vehicle used for inspecting and for connecting the new units to the submarine infrastructure.

You can read all details of the operation in the daily reports published in our ORCA-blog.

Data taking with 10 detection units has been started!

One of the new detection units of ORCA outboard of Castor, preparing to its journey to the seafloor, 2,500 m below.


Sea campaign completed: 10 detection units in operation at ORCA

22 November 2021 – Excellent progress today, with the work finalized on the two detection units lately deployed: after a confirmation from the tests that both were ok, the unfurling was started of the two units. The launcher vehicles were safely recovered from the Castor; the ROV inspected both units after unfurling, confirming that both are in nominal configuration. A new functionality test was then performed from the shore station to ensure that both detection units work nominally.

As the sea condition rapidly degraded during the day, it was decided to quit the campaign. The remaining detection units on deck will be saved for next time.

The final outcome of the campaign is: ORCA enlarged from 6 to 10 detection units!

The KM3NeT Collaboration is grateful to the heroic teams who have made such great effort onboard the two ships and in the shore station, as well as to all institutes which contributed to the construction of the detection units. We look forward to the next deployment campaign. Having said that: it’s time to resume data taking with an enlarged ORCA-10 now!

Approaching the ORCA submarine junction box at 2,500 m depth – in the foreground is the connector that the ROV is preparing to plug on it.
The team onboard the Janus – on one of the screens is the sonar image of the ORCA telescope, showing the nodes and the detection units on the sea floor. Note that the operation was performed respecting all applicable rules for protection against COVID-19 – the team got so close together only for the purpose of the picture.
The team onboard the Castor showing the ’10’ sign in front of a recovered launcher vehicle.
The onshore team. The featured instrument is an Optical Spectrum Analyser, showing the signals of the 10 detection units of ORCA. Note that the operation was performed respecting all applicable rules for protection against COVID-19 – the team got so close together only for the purpose of the picture.

News from the ORCA campaign – hard work ongoing, bad weather approaching

21 November 2021 – The weather forecast does not look promising for next days. The main effort today was spent on some tuning of the equipment and preparation to next steps.

The situation at the sea bottom is: two new detection units have been already added to the ORCA detector; a third one, after installation, connection and test, is awaiting unfurling, and a fourth one is also on the sea floor awaiting to be connected – next step will be to connnect this one.

The video shows the overboarding of the ROV from the Janus – this takes place by means of a so-called A-frame (the structure at the stern of the ship which, rotating, reaches outboard).


Two new detection units added to ORCA… and counting

20 November 2021 – It was night and day again. The work continues around the clock when you are at sea. The second detection unit was also deployed, connected and tested last night. After that, unfurling was performed for the two detection units. A final test was then made from the shore to check that the two units are ok even after unfurling, et… voilà:  ORCA is enlarged to 8 detection units.

The campaign is now continuing with deployment of the next detection units; a third one is already on the sea bottom, connected and tested. A fourth one has been deployed in the evening: we will keep going until the deck is empty or the weather changes (the forecast is not ideal for next week): which of the two will happen first?

After unfurling of a detection unit, the launcher vehicle on which the unit is installed for deployment reaches the surface and is recovered for next campaigns.
Inspection of a detection unit, after touchdown on the sea floor (~2,500 m depth). The unit featured here is the fourth one which has been deployed in this campaign.